1. Interfering float is the difference between _____.

[A] Total float and independent float
[B] Total float and free float
[C] Free float and independent float
[D] Independent float and free float

Answer: Option B

 

2. The time by which the completion of an activity can be delayed without affecting the start of succeeding activities is called ______.

[A] Total float
[B] Interfering float
[C] Independent float
[D] Free float

Answer: Option D

 

3. The full form of acronym CPM is:
[A] Construction Project Method
[B] Critical Project Method
[C] Critical Path Method
[D] Critical Program Method

Answer: Option C

 

4. The CPM network analysis is a ____ based method useful for ____.

[A] activity, research and development projects
[B] event, construction projects
[C] event, research and development projects
[D] activity, construction projects

Answer: Option D

 

5. Free float is mainly used to _____.
[A] Identify the activities which can be delayed without affecting the total float of the preceding activity
[B] Identify the activities which can be delayed without affecting the total float of the succeeding activity
[C] Identify the activities which can be delayed without affecting the total time of the project
[D] Identify the activities which can be delayed without affecting the total profit of the project

Answer: Option B