Construction Planning and Management MCQs -3 | Civil Engineering MCQs | Competitive Exams
1. The system of organization introduced by F.W. Taylor is known as _____.[A] Effective Organization[B] Functional Organization[C] Line Organization[D] Line…
1. The system of organization introduced by F.W. Taylor is known as _____.[A] Effective Organization[B] Functional Organization[C] Line Organization[D] Line…
1. Mile stone chart is an improvement over ______. [A] Bar chart[B] OPST scheduling[C] CPM Scheduling[D] PERT scheduling Answer: Option…
1. Preliminary project report for a road project must contain ______. [A] The detailed estimated cost based on detailed design[B]…
1. For pre-tensioned prestressed concrete, the grade of concrete shall be not less than[A] M30[B] M40[C] M60[D] M50 Answer: Option…
1. As per IS 456, the minimum cover to be provided for columns is[A] 50 mm[B] 25 mm[C] 40 mm[D]…
1. As per IS 456:2000, minimum period before striking form work for vertical surface of the columns _____.[A] 1 days[B]…
1. Uniformly distributed load on a concrete beam can be effectively counterbalanced by selecting _____.[A] Concentric cable[B] Eccentric cable[C] Parabolic…
1. The maximum deflection due to load in RCC beams in buildings is limited to _____. [A] Span/100[B] Span/250[C] Span/350[D]…
1. A doubly reinforced beam is considered as less economical as compared to a singly reinforced beam because _____.[A] The…
1. The maximum percentage reinforcement in beam shall not exceed of cross-sectional area as per IS:456.[A] 2.00%[B] 0.15%[C] 4.00%[D] 0.12%…