1. Preliminary project report for a road project must contain ______.

[A] The detailed estimated cost based on detailed design
[B] The several alternatives of the project that have been considered
[C] The soil survey, traffic survey, concept design and approximate cost
[D] The contract documents for inviting tenders

Answer: Option C

 

2. The process/phase of project management in which difference between the plan and actual performance are reviewed after the project is started is called _____.

[A] Planning
[B] Scheduling
[C] Controlling
[D] All of the above

Answer: Option C

 

3. The nature of tasks assigned to construction project management consultant generally includes _____.

[A] Promoting and financing the project
[B] Preparing architectural and structural drawings
[C] Tendering, supervising works and controlling of project time, cost and quality 
[D] Supplying key equipments

Answer: Option C

 

4. Which of the following parameters is not a part of typical construction project lifecycle till commissioning?

[A] Mobilization stage
[B] Operation and maintenance stage
[C] Construction stage
[D] Formulation stage

Answer: Option B

 

5. Which of the following represent the construction management functions?
(i) Planning
(ii) Marketing
(iii) Controlling
(iv) Organizing

[A] Only (i) and (ii)
[B] (i), (ii) and (iii)
[C] Only (ii) and (iii)
[D] (i), (iii) and (iv)

Answer: Option D