1. In time-cost optimization of a project, crashing is done _____.
[A] on all the activities 
[B] on original critical activities and those that become critical at any stage of crashing in order of  ascending cost slope
[C] on all activities lying on the original critical path
[D] only on activities lying on original critical path and having flatter cost slopes

Answer: Option B

 

2. Figure below shows the network for a particular project which consists of four activities

Normal Time and Crash Time for each activity are given below:

Activity

Normal Time (days)

Crash Time (days)

1-2

3

2

2-3

4

2

2-4

5

4

3-4

7

5

The minimum time required for the completion of project is _____.
[A] 9 days
[B] 13 days
[C] 14 days
[D] 19 days

Answer: Option A

 

3. The optimistic, most likely and pessimistic time estimates of an activity are 5, 10, 21 days. What is the expected time and standard deviation?
[A] 12, 3
[B] 11,4
[C] 11, 2.67
[D] 10, 16

Answer: Option C

Solution:

to = 5 days, tm = 10 days, tp = 21days
Expected time, te = (to + 4 tm + tp)/6
= (5 + 4×10 + 21)/6
= 11 days
Standard deviation σ = (tp – to)/6
= (21-5)/6
σ = 2.67 days

 

4. Slack is given as the difference between _____.

[A] Latest allowable occurrence time and earliest expected time
[B] Latest allowable time and pessimistic time estimate
[C] Earliest expected time and latest
[D] Final event time and initial event time allowable time

Answer: Option A

 

5. If the probability factor is zero, the chances of completing the project in scheduled time are ______.
[A] 0%
[B] 50%
[C] 75%
[D] 100%

Answer: Option B

 

 

CPM MCQs 👇

Leave a Reply

Your email address will not be published. Required fields are marked *