Construction Planning and Management MCQs -11 | Civil Engineering MCQs | Competitive Exams
1. In case of a unit-price contract, if a contractor quotes higher rates for some items and lower for the…
1. In case of a unit-price contract, if a contractor quotes higher rates for some items and lower for the…
1. The volume of soil to be excavated in its in-place natural state is called _____. [A] Compacted cubic meter[B]…
1. If an activity has its optimistic, most likely and pessimistic times as 2, 4 and 9 respectively, then its…
1. The full form of PERT method of project network analysis is ______. [A] Project Estimation and Review Technique[B] Programme…
1. In time-cost optimization of a project, crashing is done _____.[A] on all the activities [B] on original critical activities and…
1. The reduction in project time normally results in: [A] Increasing the direct cost and decreasing the indirect cost [B]…
1. Interfering float is the difference between _____. [A] Total float and independent float[B] Total float and free float[C] Free…
1. A ____ is similar to an activity but it does not consume any resources.[A] Dummy[B] Event[C] Slack[D] None of…
1. The system of organization introduced by F.W. Taylor is known as _____.[A] Effective Organization[B] Functional Organization[C] Line Organization[D] Line…
1. Mile stone chart is an improvement over ______. [A] Bar chart[B] OPST scheduling[C] CPM Scheduling[D] PERT scheduling Answer: Option…