1. Cast iron piles _____.
[A] resist shocks or vibrations
[B] are suitable for use as batter piles
[C] are useful for heavy vertical loads
[D] are suitable for works under sea water
Answer: Option C
2. The process of filling hollow spaces of walls before plastering, is known as ______.
[A] Blistering
[B] Hacking
[C] Peeling
[D] Dubbing out
Answer: Option D
3. The platform at the end of a series of steps, is known as _____.
[A] Rest
[B] Landing
[C] Relief
[D] Platform
Answer: Option B
4. The type of arch generally constructed over a wooden lintel or over a flat arch for the purpose of carrying the load of the wall above is _____.
[A] Relieving arch
[B] Segmental arch
[C] Flat arch
[D] Pointed arch
Answer: Option A
5. The form work from the slabs excluding props, can be removed only after _____.
[A] 14 day
[B] 7 day
[C] 4 day
[D] 1 day
Answer: Option C