1. Preliminary project report for a road project must contain ______.
[A] The detailed estimated cost based on detailed design
[B] The several alternatives of the project that have been considered
[C] The soil survey, traffic survey, concept design and approximate cost
[D] The contract documents for inviting tenders
Answer: Option C
2. The process/phase of project management in which difference between the plan and actual performance are reviewed after the project is started is called _____.
[A] Planning
[B] Scheduling
[C] Controlling
[D] All of the above
Answer: Option C
3. The nature of tasks assigned to construction project management consultant generally includes _____.
[A] Promoting and financing the project
[B] Preparing architectural and structural drawings
[C] Tendering, supervising works and controlling of project time, cost and quality
[D] Supplying key equipments
Answer: Option C
4. Which of the following parameters is not a part of typical construction project lifecycle till commissioning?
[A] Mobilization stage
[B] Operation and maintenance stage
[C] Construction stage
[D] Formulation stage
Answer: Option B
5. Which of the following represent the construction management functions?
(i) Planning
(ii) Marketing
(iii) Controlling
(iv) Organizing
[A] Only (i) and (ii)
[B] (i), (ii) and (iii)
[C] Only (ii) and (iii)
[D] (i), (iii) and (iv)
Answer: Option D